Procurement Management Practice Questions
Master Procurement Management for the PMP exam with comprehensive practice questions, detailed explanations, and proven study strategies.
1,800+
Practice Questions
91%
Pass Rate
75K+
Students Passed
What You'll Learn
Procurement Management is a crucial knowledge area within the Project Management Professional (PMP) exam. This topic covers the processes involved in purchasing or acquiring products, services, or results needed from outside the project team to perform the work. Effective Procurement Management ensures that the right goods and services are obtained at the best possible price, while also managing the relationship with the selected vendors or suppliers. Understanding Procurement Management is essential for PMP candidates, as it helps them navigate the complexities of sourcing and contracting to successfully deliver projects.
Key Concepts
Plan Procurement Management
The process of documenting project procurement decisions, specifying the approach, and identifying potential sellers.
Conduct Procurements
The process of obtaining seller responses, selecting a seller, and awarding a contract.
Control Procurements
The process of managing procurement relationships, monitoring contract performance, and making changes and corrections as appropriate.
Close Procurements
The process of completing each project procurement, including the settlement of any open items and closing each contract.
Procurement Documents
The documents used in the procurement process, such as requests for information (RFIs), requests for proposal (RFPs), requests for quotation (RFQs), and contracts.
Make-or-Buy Analysis
The process of determining whether to obtain a product or service from outside the organization (buy) or to have the project team produce it (make).
Contract Types
Different types of contracts, such as fixed-price, cost-reimbursable, and time and materials, which have different levels of risk and responsibility for the buyer and seller.
Common Mistakes to Avoid
- Failing to properly plan the procurement process, leading to ineffective or inefficient sourcing and contracting.
- Not considering all relevant procurement documents and their specific requirements when selecting a seller.
- Neglecting to monitor and control the procurement process, resulting in issues with vendor performance or contract compliance.
- Overlooking the importance of close-out procedures for completed procurements, leading to unresolved issues or incomplete records.
- Misunderstanding the different types of contracts and their implications for risk management and project success.
Sample Procurement Management Questions
Question 1
Which of the subsequent options does NOT represent a tool or technique utilized during the Conduct Procurements process?
Audits
(Correct)Bidder conferences
Interpersonal and team skills
Advertising
Explanation:
Correct answer: Audits Tools and techniques employed during the Conduct Procurements process include: Expert judgment Advertising Bidder conferences Data analysis Interpersonal and team skills Audits are instead a tool or technique applied during the Control Procurements process.
Question 2
All listed are tools and techniques employed in the Control Procurements process, except:
Work performance data
(Correct)Audits
Claims administration
Inspection
Explanation:
Correct answer: Work performance data Tools and techniques in the Control Procurement process include: Expert judgment Claims administration Data analysis Inspection Audits Work performance data is used as input for various processes, including Control Procurements, but is not itself a tool or techn...
Question 3
Which pair of elements is considered input to the Conduct Procurements process?
Project management plan; Procurement documents
(Correct)Procurement management plan; Approved change requests
Procurement management plan; Agreements
Agreements; Procurement documentation
Explanation:
Correct answer: Project management plan; Procurement documents Inputs to the Conduct Procurements process include: Project management plan Project documents Procurement documentation Seller proposals Enterprise environmental factors Organizational process assets Agreements and Approved change reques...
Study Tips for Procurement Management
Familiarize yourself with the key procurement processes and their inputs, tools and techniques, and outputs.
Practice identifying the appropriate procurement documents for different procurement scenarios and understanding their purpose.
Review case studies and examples of successful and unsuccessful procurement management to understand the real-world application of these concepts.
Understand the different contract types and their advantages and disadvantages, as well as the factors that influence the selection of a contract type.
Carefully review the procurement-related questions in PMP practice exams and analyze the reasoning behind the correct answers.
Ready to Start?
Get instant access to all Procurement Management practice questions with detailed explanations.
Start Free TrialNo credit card required
Related PMP Topics
PMP Question Types
Frequently Asked Questions
How many Procurement Management questions are on the PMP?
Procurement Management is an important component of the PMP exam. Upsero includes hundreds of practice questions covering all aspects of this topic.
How do I study for Procurement Management?
Start with understanding the key concepts, then practice with realistic exam questions. Upsero's ReadyScore tracks your mastery of Procurement Management so you know when you're ready for the real exam.
Are the practice questions similar to the real PMP?
Yes! Our Procurement Management questions are designed to match the exact format, difficulty, and style of the actual PMP exam. Many students say our questions are even harder than the real exam.
Master Procurement Management Today
Join thousands of students who passed the PMP with Upsero
Start Free Trial